Environmentalists file complaint over Kosovo’s coal project

Tuesday, 14 May 2019



PRISTINA, May 13 (Reuters): Environmentalist groups on Monday filed a complaint with the European Union's energy watchdog challenging the legality of a power purchase agreement for a planned $1.3 billion coal-fired power plant in Kosovo.
Kosovo and London-listed power firm ContourGlobal picked on May 3 a consortium of General Electric subsidiaries to build the 500-megawatt plant, which is designed to meet nearly half of Kosovo's power demand.
The Kosovar government has committed to buying the total output of the plant and the 20-year power purchase contract awaits ratification by the Balkan republic's parliament.
But environmental activists fear the deal would strain the state budget and lead to higher costs for consumers.