logo

Foreign Ministry to follow direct procurement rule

Saturday, 5 April 2014


Cabinet Economic Affairs Committee turned down a proposal of the Foreign Ministry to follow Japanese law in appointing contractor for the construction of Bangladesh chancery complex in Tokyo, reports UNB.
Rather, the cabinet body asked the Foreign Ministry to go for direct procurement process under the purview of Bangladesh public procurement law (PPA) 2006.
In its proposal, the ministry sought the waiver from the Bangladesh law and instead following the Japanese law in this connection.
"The cabinet body found no basis within its jurisdiction to accept the Foreign Ministry's proposal to follow the Japanese Law instead of the Bangladesh law," said Nurul Karim, additional secretary of the Cabinet Division.
He said the Bangladesh embassy in Japan would have to follow native law in dealing with any procurement proposal.
Official sources said the Foreign Ministry's proposal came against the backdrop of its failure to appoint a contractor to build Bangladesh chancery complex in Tokyo for which Japan government has allocated a piece of land in Tokyo with a condition to build the complex within a specific timeframe.
The construction of the chancery complex in Tokyo is a longstanding project as it was undertaken in 2011 following the allotment of land from the Japanese government.
Executive Committee of the National Economic Council (ECNEC) approved the project of Tk 886.4 million for implementation between July 2011 and June 2013.
However, the construction cost of the complex was estimated to be Tk 777.8 million.
Following the ECNEC approval, Bangladesh Embassy in Japan invited a tender and a number of Japanese construction companies showed interest in the project. Finally, three Japanese firms emerged as pre-qualified bidders for the project.
But, when these three firms were asked to submit their respective offers by 18 December 2013, two of them-Shimizu Corporation and ANDO Corporation-surprisingly informed the embassy that they would not submit tender for the project.
Of them, Shimizu Corporation said that the tender was invited as per Bangladesh procurement law. But it is not possible for them to follow the Bangladesh law in any construction work in Japan.
Only one Japanese firm-CHIKEN Company Limited-submitted its offer, but refrained from submitting any security bond along with the offer. As a result, the offer of the lone bidder was also cancelled.
The whole process put the Bangladesh embassy in a great trouble as there was a condition from Japan while allotting the land that the Bangladesh would have to build its chancery complex within a specific timeframe of 30 June 2012. In case of failure, it has to pay a penalty of 111.7 million Japanese yen to the Japan government.
However, after a long parley, the Japanese government finally extended theĀ  construction timeframe until June 2014. Now again, the Bangladesh government requested the Japanese government to further extend the time up to July 2016.