logo

India disallows Reliance from cost recovery of $2.4b

Nidhi Virma of Reuters from New Delhi | Thursday, 17 July 2014


India has disallowed Reliance Industries Ltd from recovering $2.376 billion invested to develop offshore gas fields in the D6 block on the country's east coast as output has fallen drastically and is way below the promised volumes, the oil minister has said.
Under India's exploration policy, the government allows companies to first recover their costs from oil and gas revenue, and subsequently share profits with the government.
Reliance had set up facilities to produce 80 million cubic metres a day (mmscmd), but actual gas production has been much lower, resulting in underutilisation and creation of surplus inventories, Dharmendra Pradhan has told lawmakers in a written reply. He said notices were being issued to Reliance, which is the block operator, for disallowance of cost recovery.
The D1 and D3 gas fields in the block were to produce at a peak rate of 80 mmscmd in 2012-13 but actual production never reached that level. In April-June this year, production from the two fields averaged just 8.05 mmscmd, he said.
The government disallowed Reliance to recover $1.797 billion as of March 2013, which had risen to $2.376 billion by March 2014, Pradhan said.
Because of disallowance of cost recovery to Reliance and its partners BP and Niko Resources, the government raised an additional claim of $195 million as profit for a period up to March 31, 2014, Pradhan said.
Reliance had said earlier that unexpected geology caused the decline in output and drilling more wells would not help, but this has been rejected by the oil ministry, which believes output has fallen due to non-drilling of the promised number of wells. "The issue is currently under arbitration," he said.