KURIGRAM, Oct 22 (UNB): Three hundred families in Chilmari upazila of Kurigram district have been without power for the past two weeks.
Sources said the submarine cable and electric poles were under threat of river banks erosion in Chilmari upazila, prompting the authorities to disconnect power from the main grid two weeks back.
Despite the crisis the Palli Bidyut office has yet to take any initiative to restore the power connection.
Local residents alleged negligence from the local power office saying that government property worth Tk several crores is now at risk of further damage from the erosion.
Aminul Islam, chairman of Chilmari union, said they had informed the Deputy General Manager and the engineer of the local power office about the erosion but no steps have been taken yet.
Md Alamin, assistant general manager of the Chilmari Zonal office, said they are unable to repair the line independently as it requires a formal plan.
300 families go without power in Kurigram for two weeks
Authorities have disconnect power as submarine cable and electric poles are under threat of river banks erosion
FE Team | Published: October 22, 2024 22:36:16