Some 30 per cent construction work on the 1200MW Matarbari coal-fired power plant was completed as of July last as Coal Power Generation Company Bangladesh Limited (CPGCBL), the implementing agency, has a target to complete the most expensive scheme by June 2023, shows an official document, reports UNB.
The document was placed at a progress review meeting of the annual development programme (ADP) of the Power Division on August 31.
However, officials at the implementing agency claimed that the progress in the project work was 37 per cent as of August.
They said though the coronavirus pandemic was a great concern, it had little impact on the project work.
"We're making good progress as per our schedule and hope to be able to cover the work hampered for a few months due to the pandemic," CPGCBL managing director Abdul Mutalib told the news agency.
On completion of land development, he said, now piling and other civil construction work was being carried out at the project site.
The Executive Committee of the National Economic Council (ECNEC) approved the project titled 'Matarbari 2x600 MW Ultra Super Critical Coal Fired Power Plant' involving TK 35,984.46 crore (equivalent to $4.5bn) in 2014.
It is considered to be the country's most expensive power generation project as it has included the construction of a berthing port for handling imported coal.
Japan International Cooperation Agency (JICA), a Japanese donor agency, is providing Tk 289.39 billion (28,939 crore) for the project located at Matarbari and Dhalghata under Moheshkhali upazila in Cox's Bazar while CPGCBL will finance Tk 49.26 billion (Tk 4,926 crore) from its owned fund.
CPGCBL officials said the Matarbari project would be an Ultra Super Critical Technology (USCT)-based power plant with 41.99 per cent energy efficiency against the average 34 per cent efficiency of coal-power projects.
They said the main activities of this project, having two units each with a capacity of 600 MW, are construction of power plant (civil), jetty and channel, setting up of power plant boiler (EPC part), establishment of power plant turbine and generator (EPC part), and power plant coal and produced ash management (EPC part).
The Matarbari thermal power plant will be developed on a 1,500-acre site with two thermal units based on ultra-supercritical coal-fired technology, having an installed capacity of 600MW each.
The Matarbari power plant project was conceived in the government plan in September 2011 and received environmental approval in October 2013. The ground-breaking ceremony for the project was held in January 2018 as its operation is expected to begin by June 2023.
Officials said a new deep-sea port facility named Matarbari Port would be developed for importing the coal required for the power plant which will include a 760m-long container and a multi-purpose terminal.
The port terminal will include a fuel berth, fuel transportation facility, and two coal-handling jetties. The channel length will be 14km, while the width 250m and the maximum depth approximately 18.5m.
CPGCBL officials said the power plant may require 3.73 million tonnes (Mt) of coal a year, which will be imported from Indonesia, Australia and South Africa through the Matarbari Port.